SECTION 8 Tailing Storage Facility 3 C:\D Data\GWS C Drive\GWS\Client Files\1344 OGL - WKP\4 Deliverables\WUG Effects Summary\June 2022\WNP Groundwater Effects Summary_Final_Rev_0.docx 33 Figure 36 TSF3 Groundwater Flow Paths During and Following Construction (From GHD 2022) Monitoring Monitoring of groundwater levels and quality is proposed as well as surgace water flow gaugings and water quality. Specific requirements will be detailed in an overarching Water Monitoring and Contingency Plan. The plan will include requirements for baseline monitoring (for comparative analysis to provide a degree of confidence in the assessment), trigger levels, and contingency measures to manage any potential exceedances.
RkJQdWJsaXNoZXIy MjE2NDg3