Site-specific Assessments of Environmental Effects

B-6 – Area 6 – Assessment of Environmental Effects 29 Figure 15: Location of Proposed Topsoil Stripping and Topsoil Stockpiles. The two northern topsoil stockpiles will together contain up to 170,500 m3 of material and will be constructed to a nominal height of 10 m above natural topography. The northern toe of the topsoil stockpiles will be defined by the current alignment of the overhead electricity transmission line that runs parallel to Golden Valley Road. The eastern most of these stockpiles has been designed to act as a noise barrier between the NRS and properties to the north. The western stockpile will contain up to 14,000 m³ of material and will be constructed to a nominal height of 10 m above natural topography. Erosion and sediment control measures will be adopted during the work in accordance with Section 3.2.5, below.