Site-specific Assessments of Environmental Effects

B-6 – Area 6 – Assessment of Environmental Effects 28 Figure 14: The NRS Location and Footprint (EGL (2022d)). 3.2 PREPARATORY WORKS 3.2.1 Topsoil Stripping and Stockpiling The maximum footprint of the NRS will require approximately 24 ha of topsoil to be progressively stripped, including several unnamed stream beds. Stripped topsoil will be held in stockpiles as depicted in Figure 15.

RkJQdWJsaXNoZXIy MjE2NDg3